The COTN Timeline

The COTN Timeline

We've included the COTN timeline to help everyone keep track of the events and their completion. Following the timeline changes will help other sites plan their projects by seeing which can be done quickly and which need more time.

The COTN Timeline: 


Target Date
Activity
Complete
November, 2013
Hire and train RN Case Manager and CHW Positions
X
November, 2013
Conduct the Readiness Survey with Mosaic CHC Key Stakeholders
X
November, 2013
Conduct on-site education sessions with providers at each CHC
X
November, 2013
Designate 100 Remote Monitoring units to Mosaic CHC
X
November, 2013
Distribute and train Roanoke's proprietary implementation manuals to Mosaic CHC
X
November, 2013
Conduct on-site training to review implementation manual for RN Care Coordinator and CTO along with informing on quality indicators
X
November, 2013
Assign RN Care manager and CHWs to appropriate sites
X
November, 2013
Establish TRPM Advisory Committee and Strategic Planning/Development Workgroup

November, 2013
Implementation meeting with RN Care Coordinator and CHWs for equipment and software training
X
November, 2013
Perform conference calls to finalize and approve all necessary components of the program’s process (policy/procedures/patient selection, enrollment, informed consent/data collection procedures and tools/nurse and patient competency forms)
X
November, 2013
See Enrollment – Discharge Plan for all grant active remote patient monitoring activities following this table below

October, 2014
Conduct monthly conference calls with all sites to discuss issues, resolutions, and provide program updates
      X
October, 2014
Scope and build interface between TRPM solution and OCHIN Epic HER

October, 2014
Develop and provide outreach and education to COHC members for referral to Mosaic TRPM program

October, 2014
Perform on-site training to review and   
revise implementation manual            
      X
September, 2014
Analyze and report on year one data for operational and clinical efficacy and cost savings

September, 2015
Analyze and report on year two data for operational and clinical efficacy and cost savings

September, 2015
Perform on-site training to review and revise implementation manual

October, 2015
Conduct bi-monthly conference calls with all sites to discuss issues,
resolutions, and provide program       
updates
     X
October, 2015
Provide logistical support to COHC members to ensure effective referrals to Mosaic TRPM program

October, 2015
Review and revise data ingest and reporting requirements for clinical and financial information

September, 2016
Conduct quarterly conference calls with all sites to discuss issues, resolutions, and provide program updates

September, 2016
Provide logistical support to COHC members to ensure effective referrals to Mosaic TRPM program

September, 2016
Review and revise data ingest and reporting requirements for clinical and financial information

September, 2016
Analyze and report on year three data for operational and clinical efficacy and cost savings (baselines and program metrics for 500 unduplicated patients)

September, 2016
Project close out including program and financial reporting